Playground in Mollstraße, Berlin

Typology: Playground

Project Manager I SCHÖNHERR

RIBA Stage 2 – RIBA Stage 4: 2021 - 2022

Planning: 2020 - 2022

Construction: 2022 - 2024

Scale: 2.400 m²

Budget: 680.000 €

This site has the particularity of holding underground a multiplicity of pipelines of gas, electricity, water. In the context of a tight timeline, due to the nature of the allocated public subsidies, a swift coordination with the different suppliers took place.

I developed the design baseline for the Request for Proposal. From the 3 playground manufacturers invited, the manufacturer Spiel AHOI received the tender.

#Project Management #Citizen Participation #Building Design